How to Apply a Prepayment Adjustment to an AP Bill

Follow these Steps to Apply a Prepayment Adjustment to an AP Bill

When a Purchase Order has a prepayment attached, Acumatica automatically associates it with the connected Invoice.

  1. First, associate the Bill with the Purchase Receipt.
  2. On the Bills and Adjustments screen, open the Applications tab.
  3. Select the prepayment associated with the Purchase Order that you want to apply to the bill.

Open the Applications tab on the Bills and Adjustments screen

  1. Enter the amount of the prepayment that you want to apply to the Bill.

Enter the amount of the prepayment that you want to apply to the bill.

Note: Acumatica calculates the prepayment balance when the Amount paid is less than than the total prepayment.

  1. Finally release the Bill.

Note: In our example below, the balance due is less than the amount paid by the prepayment.

Release the bill.